Pre Development Services – Waste Water

Banner image

If you are planning a new development, you’ll need to talk to us in the early stages of planning so that we can avoid delays and provide support and advice on your proposal.

Before construction can begin, most types of development or building work will need planning permission from the local planning authority.

Whilst we are not a statutory consultant for planning applications, we endeavour to review all applications for planning permission that are submitted to local authorities. We do this to ensure that any development does not compromise our assets including water and waste water networks, which ultimately protects the service we supply to our customers.  Please click here to view the Planning Application Standard Requirements.

The pre planning process provides the customer with the point of connection for the site they are looking to developer and a budget estimate of the costs of supply them.
The company will provide:

  • A copy of the public records and a point of connection
  • A desktop estimate based on the Developer Services Charging Arrangements

This information will be provided within 21 calendar days of a full application.

Customers can undertake their own point of connection assessment and should they require validation of this review, the information can be submitted to South West Water for validation. 

Application form

Pre Planning Point of Connection Application Form

Please complete all sections and provide the information requested so that your application can be processed as quickly and accurately as possible.

Online Payment and other payment methods

Payment online

Once you have been assigned your unique WR number from a member of the pre-development team, the quickest method is payment online.

 

Please check your application form for the total amount payable for your enquiry.

 

Click here to access online payment, please ensure all information requested is populated.

 

Alternatively, the following payment methods can be used:-

 

Credit/Debit card over the phone
To pay by credit or debit card please call our Helpline on 0800 083 1821 between the hours of 9am and 4pm Monday to Friday.
*American Express (Amex) and Via Electron are not accepted.


BACS
If you would like to make payment by BACS, South West Water’s bank details are as follows:


Bank Name and Address

Lloyds TSB Bank Plc
City Office, Corporate & Institutional
PO Box 72
Bailey Drive
Gillingham Business Park
Kent ME8 0LS


Bank Sort Code

30-00-02


Bank Account Number

00456492


Bank Account Name

South West Water Ltd Collection Account

 

To avoid a delay in processing the payment, please enter your Work Request number as a reference. This allows your payment to be identified and linked to your enquiry.


You will also need to send in remittance advice (either your own generated remittance or an email to our Sales Ledger Team zzSalesLedger@southwestwater.co.uk ) 

 

Remittance advice information

Your advice should contain the following information:


• Your name & address (company or individual of the bank account where the payment is coming from)
• Your contact telephone number
• Your reference number (i.e. your internal reference number, a supplier number from South West Water or a job number applicable to the work)
• Date of remittance
• Date payment made
• Date payment expected in South West Water’s bank account
• Our reference – Work Request Number
• Payment amount


Payment will clear and show on South West Water’s system within 4-5 working days and you will be issued with an invoice upon receipt of your remittance advice.


Cheque
If you would prefer or pay by cheque please make it payable to South West Water, write your Work Request Number on the back and send to:


Developer Services – Planning Team
South West Water
Peninsula House
Rydon Lane
Exeter
EX2 7HR


You will need to allow 10 working days for the payment to clear

 

Please note - Full payment must be received before we can process your enquiry.

Flowchart and charges

Information on our Developer Services Charging Arrangements can be found here.

Please view 'Customer Flowchart - Pre Planning Point of Connection Enquiry' for more information.

Our performance

Levels of Service
Our minimum standard for delivery will be in accordance with the Water UK Levels of Service.

 

Metric 

Target Timescale (days) 

Pre-development enquiry – reports issued

21

 

 
Redress - Adoption of clean water assets

Although we pride ourselves on the service we provide to our SLP customers, on occasion we may fall short.
For further information on these standards and to see our performance please click here.

Metric 

Target Timescale (days) 

Form of Redress

Self-lay point of connection -written acknowledgements issued within a period of 5 days commencing on the day after receipt confirming either that the application is completed or if not , requesting the missing information.  5 Contact from the Developer Services team to agree next steps
Self-lay Point of Connection reports <500 plots etc. - reports issued. Report to be issued within 21 days commencing on either (i) on the day after receipt of a full application or (ii) the day after the required information has been provided .   An application is full when all the required information and any required payment have been received .  A Pock enquiry includes any necessary modelling work.   21 Refund of that element of the application fee up to a maximum of £120 
Self-lay Point of connection reports >500 plots etc. - reports issued .Report to be issued within 28 days commencing on either (i) on the day after receipt of a full application or (ii) the day after the required information has been provided.  An application is full when all the required information and any required payment have been received   A PoC enquiry includes any necessary modelling work.  28 Refund of that element of the application fee up to a maximum of £120 
Self-lay design approval and terms request application - written acknowledgements . Issued within a period of 5 days commencing on the after receipt confirming either that the application is complete or if not ,requesting the missing information.  5 Contact from the Developer Services team to agree next steps 
Self-lay and terms requesting <500 plots etc. quotations. Written terms to be issued within a period of 14 days commencing on the day after receipt of as full application.  An application is full when all the required information has been received. Terms include the design approval ,the amount of the asset payment and any amount to be paid by the SLP or Developer . A self-lay Adoption Agreement is to be issued with the terms. Rejections should fully document the reason for the rejection.  14 Refund of that element of the application fee up to a maximum of £180
Self-lay and terms requesting >500 plots etc. quotations. written terms to be issued within a period of 14 days commencing on the day after receipt of a full application.  An application is full when all the required information has been received. Terms include the design approval ,the amount of the asset payment and any amount to be paid by the SLP or Developer . A self-lay Adoption Agreement is to be issued with the terms. Rejections should fully document the reason for the rejection.  28 Refund of that element of the application fee up to a maximum of £180 
Self-lay signed agreement - acknowledgements. Issued within a period of days commencing on the day after receipt of the signed agreement  5 Contact from the Developer Services team to agree next steps 
Self-lay water for pressure/bacteriological testing - provided. Provide a source of supply for pressure and bacteriological testing within (i) 28 days commencing on the day after receipt of a written request or 9ii0 such longer period as may be agreed with the SLP where there are engineering difficulties /requirements for off-site reinforcement/Schedule 13 WIA 1991 constraints or where the SLP requests an extended period.  28 £100 for each week up to a £2000 limit
Self-lay permanent water supply - provided. Provide a permanent supply connection within 14 days commencing on the day following notification in writing of satisfactory pressure and bacteriological testing of the self-lay mains.  14 £100 for each week up to a £2000 limit
Self-lay vesting certificates - issued . Issue vesting certificate and all information for Asset Payments claim (including on part constructed work) within 7 days commencing on the day following notification that the section of main has been connected.  7 Refund of that element of the application fee up to a maximum of £90
Self-lay Asset Payments - issued. Make Asset Payment due on all sections of connected mains within 35 days commencing on the day following receipt of a valid invoice claim by the SLP.  35 £100 (one off payment)
 Self-lay plot references and costing details. Issue plot reference information and costing details within 14 days commencing on the day following written notification of (service) connections call-off by the SLP. Costing details to specify all charges payable on each service connection, including infrastructure charges and the cost associated with the provision of meters and any fittings procured from the water company.  14 Refund of that element of the application fee up to a maximum of £11

When financial redress is applicable, payments will be sent back to customer who paid for the service within 60 days of the Levels of Service being published on Water UK’s website.

The redress scheme is a temporary arrangement, in line with the requirements of Ofwat's Code for Adoption Agreements. We are working with Water UK and all other companies to determine appropriate and consistent redress arrangements across the sector.

We will update our website on completion of this work.

Redress - Adoption of waste water assets

Although we pride ourselves on the service we provide to our SLP customers, on occasion we may fall short.

Metric 

Target Timescale (days) 

Form of Redress

Report on the number of written acknowledgements within target  14 Contact from the Developer Services team to agree next steps
Technical vetting - number of applications responded to in the period  28 (note S5.1 is including in this timescale) Contact from the Developer Services team to agree next steps
Technical vetting - number of applications responded to in the period extended by agreement  as agreed Contact from the Developer Services team to agree next steps
Legal agreements sent within period of target.  14 Contact from the Developer Services team to agree next steps

The redress scheme is a temporary arrangement, in line with the requirements of Ofwat's Code for Adoption Agreements. We are working with Water UK and all other companies to determine appropriate and consistent redress arrangements across the sector.

We will update our website on completion of this work.

 

 

Isles of Scilly

Isles of Scilly

From 1 April 2020 South West Water became the appointed water and wastewater company for the Isles of Scilly. This means that South West Water took responsibility for existing water and wastewater infrastructure on the islands.

 

Investing in our region

We believe it is right to support the necessary improvements in water and wastewater services on the islands so that services are in line with standards on mainland UK by 2025 or 2030 in the case of Tresco. This includes the ability to provide new water and sewer connections to the network.

 

Our wastewater investment will be focused on achieving a reliable wastewater service including being able to cope with extreme conditions, protecting the environment and providing long term benefits to the community.

 

The balanced investment for each island for water asset improvements will focus on achieving a clean, safe and reliable supply of drinking water.

 

South West Water appreciate that the island economy is heavily dependent on tourism with over 90% of the islands' income coming from this source. Therefore, our proposed programme of investment will be designed to support and enhance the economy of the islands by improving services and the environment. Once finalised, we will actively communicate with local communities to ensure we work together to deliver improvements in the best way for the communities we serve. Once the asset improvements are delivered to your community we will happily help with applications for new or replacement supplies.

 

Should you wish to discuss your enquiry further please contact our Developer Services Help Desk on 0800 083 1821.